Drain fall and cover check

A subsoil drain needs a fall of at least 1:300 and a silt pit with its outlet 50 mm below the inlet. A 90 mm stormwater pipe needs 100 mm of cover under soil and 50 mm under paving. Pick the drain and enter your numbers.

1:300 lineoutlet1:20060 mm over 12 m50silt pitfall drawn steeper than it is
Clause
3.3.4
Code
NCC 2022
Drawn in
mm
Pass2 of 2 checks within limits
Which drain
m
mm

How much lower the low end is than the high end.

mm

Invert of the pipe coming in, down to the pipe going out.

Checks

Pass. 2 of 2 checks within limits.

  • Fall: Within the limit.

    1:200

    1:300 or steeper3.3.4(a)

  • Outlet below inlet: Within the limit.

    50 mm

    50 mm or more3.3.4(b)

  • Silt pit: For information.

    Outside, and cleanable

    room to clean and maintain it3.3.4(b)

This checks the deemed-to-satisfy dimensions for houses (Class 1 and Class 10 buildings) in NCC 2022. State variations and your approved plans come first, and your certifier has the final say.

What the code asks for

  • Subsoil drainage goes in where the site creates a need to divert water in the ground away from footings, basements, retaining walls and the like. 3.3.2(b)
  • A subsoil drain has an even fall of at least 1:300. 3.3.4(a)
  • It discharges into a silt pit or sump outside the building, with the outlet at least 50 mm below the invert of the inlet. 3.3.4(b)
  • The silt pit has room to be cleaned and maintained. 3.3.4(b)
  • A 90 mm Class 6 UPVC stormwater drain needs at least 100 mm of cover under soil and 50 mm under paving or concrete. 3.3.5(c)
  • Where light vehicles drive over it, the cover is 75 mm under reinforced concrete and 100 mm under paving. 3.3.5(c)
  • Cover is measured from the top of the pipe to the finished ground, or to the underside of paving or concrete. 3.3.5
  • Where the stormwater discharges, and how, has to satisfy the appropriate authority. 3.3.5(a)
  • The system is designed so overflow in heavy rain cannot run back into the building. 3.3.5(b)
  • A trench for a drain beside existing footings stays inside the area the code marks as safe to dig. 3.3.2(d)

Source: Part 3.3 of the ABCB Housing Provisions (NCC 2022). The 1:300 fall, the 50 mm silt pit drop and the cover figures are the same in NCC 2025.

Questions people ask

What fall does an ag drain need?

The code calls an ag drain a subsoil drain. It needs a fall of at least 1 in 300, which is a little over 3.3 mm for every metre, and the fall has to be even along the run. A 12 m drain needs at least 40 mm.

How deep does a stormwater pipe need to be?

For a 90 mm Class 6 UPVC pipe, the top of the pipe needs 100 mm of cover under soil and 50 mm under paving or concrete. Under a driveway used by light vehicles it needs 75 mm under reinforced concrete or 100 mm under paving. Those figures are for that pipe. Other types of pipe can be laid with a different cover, or with none.

Do I need subsoil drainage?

Only where the site creates a need to divert water in the ground away from footings, basements or retaining walls. Typical spots are the uphill side of a cut and fill site, behind a retaining wall, and beside deep footings or a basement wall. In clay soil a subsoil drain can change the moisture under the footings, so there it is a last resort.

Where can the stormwater discharge?

That is for the appropriate authority to accept, so ask your council or certifier. The code gives examples that may be accepted: a legal point of discharge at the boundary, a stormwater tank, or a soakage system such as a soaker well.

Related checks